Projects

Air Separation Installation in Kraków

  • Sector: Chemical and petrochemical
  • Status: completed
  • Period of completion: 2020
  • Client: Air Liquide Global E&C Solutions France
  • Location: Kraków

Installation of equipment, tanks, flyovers, piping and participation in project commissioning, including:

  • Prefabrication and assembly of 250 tonnes of steel structure
  • Prefabrication and assembly of pipelines – 25,000 inches
  • Installation of an oxygen storage tank – LOX – with a volume of 1500m3
  • Installation of tanks, pumps and equipment – 35 pcs.
  • Installation of the cooling tower
  • Installation of MAC, GAN and GOX compressors
  • Insulation of pipelines and tanks
  • Installation of a lightweight housing