Installation of equipment, tanks, flyovers, piping and participation in project commissioning, including:
- Prefabrication and assembly of 250 tonnes of steel structure
- Prefabrication and assembly of pipelines – 25,000 inches
- Installation of an oxygen storage tank – LOX – with a volume of 1500m3
- Installation of tanks, pumps and equipment – 35 pcs.
- Installation of the cooling tower
- Installation of MAC, GAN and GOX compressors
- Insulation of pipelines and tanks
- Installation of a lightweight housing